Title: Award/Contract - BID 19-905 Rebid NW 32nd Ave Resurfacing Project 9187901, to Watson Construction Company LLC., in the amount of $1,889,147.93, plus a contingency amount of $94,457.39, for a total fiscal impact of $1,983,605.32
Attachments: 1. NW 32nd Ave Resurfacing Contract-Watson -ATF by CAO.pdf, 2. AR 19-905 REBID NW 32nd Ave Full Depth Reclamation - Project No. 918-7901.pdf, 3. DR MEMO 19-905 REBID NW 32nd Ave Full Depth Reclamation - Project No. 918-7901.pdf, 4. BR 19-905R BID Responsiveness and SBE Recap Form.pdf, 5. BT 19-905 REBID NW 32nd Ave Full Depth Reclamation - Project No. 918-7901.pdf, 6. SUBMITTAL PRICING - Watson Construction Company LLC.pdf, 7. MAP 200303 NW 32nd Ave Resurfacing.pdf, 8. BID - 19-905R PLANS NW 32nd Ave Resurfacing - Project No. 918-7901 R.pdf, 9. BID - 19-905R UWS 191216 NW32Ave ATT.pdf, 10. BID 19-905 Rebid NW 32nd Ave Resurfacing - Project No. 918-7901.pdf, 11. BA NW 32nd Ave.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Award/Contract - BID 19-905 Rebid NW 32nd Ave Resurfacing Project 9187901, to Watson Construction Company LLC., in the amount of $1,889,147.93, plus a contingency amount of $94,457.39, for a total fiscal impact of $1,983,605.32
End

Presenter:
Ramon D, Gavarrete, P.E., County Engineer 352.548.1214/Larry Sapp, 352.374.5202

Description:
Award, Contract and Budget Amendment for BID 19-905 Rebid NW 32nd Ave Resurfacing Project 9187901

Recommended Action:
Recommended Action
Approve the award, contract and Budget Amendment for BID 19-905 Rebid NW 32nd Ave Resurfacing Project 9187901, to Watson Construction Company LLC., in the amount of $1,889,147.93, plus a contingency amount of $94,457.39, for a total fiscal impact of $1,983,605.32 as the lowest, most responsible and responsive bidder meeting specifications.
End

Prior Board Motions:
January 23, 2018 - Board approved funding for the design of NW 32nd Ave.

October 1, 2018 - Board added NW 32nd Ave to the CIP list and approved budget.

Fiscal Consideration: Approval of the budget amendment will move $1,218,157 from (4) other Transportation Projects to NW 32nd Ave Project. Two of the projects are complete: Project # 9197906 - Conventional for Tower Rd from SW 8th Ave to W Newberry Rd and Project # 9197905 - Conventional for W Univ Av from SW 75th St to the East End. The third project is substantially complete: Project #63-65 - NW 43rd St. The fourth project is 73% complete as of 4/25/20: Project #63-20 - SW 8th Ave/SW 61st St Extension. The project will be funded from accounts 341.79.7910.541.63.99 and 350.79.7916.541.63.99.
Fiscal Consideration
End

Background:
The scope for the NW 32nd Ave Resurfacing Project is to mill and resurface the existing roadway, update signage and pavement markings, install mitered end sections on all side drains, and provide paved turn-outs along the corridor. The limits of the project are NW 32nd Avenue from NW 143rd Street (CR ...