Title: ZOX-03-21: Duke Energy Substation Special Exception
Attachments: 1. Application package, 2. Staff Report, 3. Presentation, 4. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

ZOX-03-21: Duke Energy Substation Special Exception

End

 

Presenter:

Mehdi Benkhatar, 352-374-5261

 

Description:

A request by Shutts & Bowen LLP, agent, for Duke Energy Florida, Inc., owner, for a special exception to allow a major utility in the Agriculture zoning district. The site has an existing utility substation and is proposing to add a new, unmanned telecommunications shelter (13’ x 17’ building within a 40’ x 40’ gated compound area). As the existing substation predates the Comprehensive Plan and ULDC (operating since 1962), it exists as a legal, nonconforming use. The site has a future land use designation of Institutional and is approximately 15.12 acres

 

Recommended Action:

Recommended Action

Staff recommends that the Board of County Commissioners approve ZOX-03-21, with the conditions and bases as listed in the staff report.

End

 

Prior Board Motions:

None.

 

Fiscal Consideration:

Fiscal Consideration

None.

End

 

Strategic Guide:

Infrastructure

 

Background:

The applicant is requesting a special exception for a major utility (Duke Energy substation). The intent of this application is to upgrade the substation with a new telecommunications equipment shelter, generator and LPG tank. The substation on site has existed since the 1960s; however, it has never received approval from the Board of County Commissioners as a major utility and has existed as a legal, nonconforming use.  Nonconforming uses cannot be expanded, per Sec. 408.12 of the Unified Land Development Code. Therefore, the Board of County Commissioners must formally approve this use as a major utility in order for Duke Energy to make the desired upgrades to the site.