Legislation Details

File #: 22-0309    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 4/4/2022 In control: Board of County Commissioners
On agenda: 5/24/2022 Final action:
Title: Award and Contract #11590 BID 22-930 for Archer Braid SunTrail Project #9197910 to Onyx Site Services, LLC Base Bid for a total fiscal impact of $1,180,423.92 for the Public Works Department
Attachments: 1. Road and Bridge Construction Agreement No. 11590 with Onyz Site Services - Archer Rd. SUNTrail.reduced.pdf, 2. 439934-1 ATT UWS Executed.pdf, 3. 439934-1 Centurylink UWS Executed.pdf, 4. 439934-1 GRU Com UWS signed.pdf, 5. 439934-1 GRU GAS UWS Executed.pdf, 6. 439934-1 GRU WWW UWS Executed.pdf, 7. BID 22-930 - PLANS-01-ROADWAY.pdf, 8. BID 22-930 - PLANS-02-SAPM.pdf, 9. BID 22-930 - PLANS-ROADWAY-PNC.pdf, 10. BID 22-930 Archer Road SUNTrail Project #9197910.pdf, 11. BT 22-930 Archer Road SUNTrail Project #9197910.pdf, 12. DR 22-930 Archer Road SUNTrail Project #9197910.pdf, 13. DS 22-930 Archer Rd (SR 24) SUNTrail Project.pdf, 14. GS AD 22-930 Archer Rd (SR 24) SUNTrail Project.pdf, 15. ITA 22-930 Archer Road SUNTrail Project #9197910.pdf, 16. SBE 22-930.pdf, 17. Supplier Anderson Columbia Co Inc.PDF, 18. Supplier Curts Construction Inc.PDF, 19. Supplier Onyx Site Services LLC.PDF, 20. Supplier VE Whitehurst & Sons Inc.PDF
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

Award and Contract #11590 BID 22-930 for Archer Braid SunTrail Project #9197910 to Onyx Site Services, LLC Base Bid for a total fiscal impact of $1,180,423.92 for the Public Works Department

End

 

Presenter:

Larry Sapp 352.374.5202, Ramon Gavarrete 352.374.5245

 

Description:

Solicitation Award and Contract #11590 for BID 22-930 to Onyx Site Services, LLC, for Archer Road SUNTrail Project #9197910. 

 

Recommended Action:

Recommended Action

Approve Solicitation Award and Contract #11590 for BID 22-930 to Onyx Site Services, LLC, for Archer Braid SUNTrail Project #9197910, as the lowest responsible and responsive bidders meeting specifications, and authorize the Chair to execute same on behalf of the County

End

 

Prior Board Motions:

8/27/2019 - BoCC approved FDOT agreement to participate in the development of bid documents, construction, and construction engineering and inspection of the Archer Braid Suntrail project from SW 75th Terrace to SW 41st Blvd. BoCC approved associated maintenance agreement that requires the County to maintain the trail in perpetuity to receive the funding. BoCC adopted resolution 19-85 which authorized the County to enter into agreement with FDOT for the construction and maintenance of the Archer Braid SunTrail project.

 

Fiscal Consideration:

Fiscal Consideration

There is sufficient funds in FDOT Grant Fund in account 329.79.7910.541.63.01 Project #9197910 to award contract.

End

 

Strategic Guide:

Choose an item.

 

Background:

The Archer Braid SUNTrail project extends the Archer Braid Trail from SW 75th Ter (Tower Rd area) to SW 41st Blvd (Celebration Pointe area) in the GRU right-of-way. The design phase was completed by FDOT.