Legislation Details

File #: 22-0365    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 4/22/2022 In control: Board of County Commissioners
On agenda: 5/24/2022 Final action:
Title: Main Street Detention Pond Outflow Filter Project: Inter-Local Agreement #13304 with Florida Department of Transportation.
Attachments: 1. Unanticipated Revenue Resolution.pdf, 2. #13304 FDOT- Alachua County Draft ILA 2022.pdf, 3. Budget Amendment 5-9-22 ADA.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Main Street Detention Pond Outflow Filter Project: Inter-Local Agreement #13304 with Florida Department of Transportation.
End

Presenter:
Shane Williams - Environmental Protection Department

Description:
This item is to approve an inter-local agreement between the County and the Florida Department of Transportation (FDOT) through which FDOT will reimburse the County a portion of the construction costs of a nutrient reducing outflow filter at a County detention pond.

Recommended Action:
Recommended Action
Approve and authorize Chair to sign inter-local agreement #13304 with FDOT, adopt resolution recognizing unexpected revenue, approve the budget amendment, and approve inter-fund loan of $86,000.
End

Prior Board Motions:
09/14/2021 the BoCC approved this project on Water Quality Project list as part of the adoption of the final resolution for the Stormwater Assessment

Fiscal Consideration:
Fiscal Consideration
This unanticipated revenue will provide reimbursement of $86,000 of project construction costs. Because this is a reimbursement agreement an inter-fund loan is necessary to temporarily cover expenses. These are additional funds being added to the existing project which is funded from Fund 146 Stormwater Management, for a total project budget $248,000.00.

Project#8205502 Main Street Detention Pond Outflow Filter

Funds: 260.55.5511.334.3000 - Revenue
260.55.5511.537.63.98 - Expenses
End

Strategic Guide:
Environment

Background:
The wet detention pond is located at the corner of NE 4th St and NW 35th Ave. The detention pond discharges into the Hogtown Creek System and receives runoff from commercial and industrial areas along North Main Street. The County has designed and permitted an ouflow filter which will increase nitrogen and phosphorus removal from water discharged from the detention pond. FDOT has agreed to contribute 40%, or $86,000, towards the total estimated construction cost of $215,000. ...