Title: Award Bid 22-990 and Contract #12037 with J.E. Decker Construction Group, LLC for Alachua County Freedom Center Hardening Renovation in an amount not to exceed (NTE) $186,211.00 for the Public Works Department
Attachments: 1. Agreement_12037_With_Alachua_County_for_Huricane_Hardening_of_Freedom_Center complete.pdf, 2. CNT ADM 12037 1st to DEM-SR00032_Alachua_County_BOCC-for_Subrecipient_Signature_3-2-2022_(002)_AC Executed.pdf, 3. CNT ADM Agreement Extending Project Deadline, 4. DR 22.990.AC Freedom Centering Hardening RVSD Department Recommendation].pdf, 5. Submittal - J E Decker Construction Group LLC.pdf, 6. BID ADM 1 22-990 FORM OF BID BOND.pdf, 7. CNT SOS per Bid 22-990 per Walker WA21003_2021-05-12_100% CD Specs.pdf, 8. CNT SOV - J E Decker Construction Group LLC.pdf, 9. OMB Journal 2022-2400 Funds 083 and 021
Related files: 22-0234, 20-0922
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Award Bid 22-990 and Contract #12037 with J.E. Decker Construction Group, LLC for Alachua County Freedom Center Hardening Renovation in an amount not to exceed (NTE) $186,211.00 for the Public Works Department
End

Presenter:
Ramon Gavarrete 352.374.5245

Description:
Award Bid 22-990 to J.E. Decker Construction Group, LLC as the lowest responsive and responsible bidder meeting specifications for Alachua County Freedom Center Hardening Renovation and authorize the Chair or Manager to execute Contract #12037, once finalized with Decker and approved by the County Attorney's Office, and any other project related documents

Recommended Action:
Recommended Action
Approve the attached Budget Amendment, approve the solicitation award for Bid 22-990, waive the Payment/Performance Bond requirement, approve Contract #12037 with J.E. Decker Construction Group, LLC, and authorize the Chair or Manager to execute same on behalf of the County, and any other project related documents.
End

Prior Board Motions:
November 10, 2020, Approval of the State-Funded Grant Agreement
March 22, 2022, Approval of Modification of Grant Agreement to increase funding

Fiscal Consideration:
Fiscal Consideration
Project: 8214101 Freedom Center Retrofit
Emergency Management Grant Fund: 083.41.4100.529.31.00 & 083.41.4100.529.46.00
This is a reimbursement-based grant from the State of Florida, $200,000. $15,550 was spent in FY21.
Expenses over the $200,000 award will be paid by Parks using Wild Spaces Public Places funding, 021.41.4100.572.46.00. A budget amendment reallocating $9,000 has been included, though the additional costs should be less than that amount.
End

Strategic Guide:
Strategic Guide
Infrastructure
End

Background:
On December 8, 2020, the State of Florida and the County entered into Grant Agreement Number F0081 for Project Number DEM-SR00032 for Hurricane Hardening of the Freedom Center at Veterans Memorial Park. The Grant Agreeme...