Agenda Item Name:
Title
Approve Budget Amendment to increase the project total by $10,000 for Lake Alto Park
End
Presenter:
Jason Maurer - Parks & Open Space Director
Description:
Approve increasing the project budget by $10,000 and the attached budget amendment for the Lake Alto Park Restrooms Project.
Recommended Action:
Recommended Action
Approve increase in project budget and the attached budget amendment.
End
Prior Board Motions:
June 9, 2020 - Award/PO - BID 20-959 Lake Alto Boat Ramp Improvements, to D&L Contracting, LLC, in the amount of $59,250.00
Fiscal Consideration:
Fiscal Consideration
Increase project cost by $10,000; the new total project cost is $110,000 entirely from Boating Improvement Funds.
Fund: 043.41.4100.572.62.00
Project 6194105- Lake Alto Park - New Construction - Restroom
End
Strategic Guide:
Strategic Guide
Infrastructure
End
Background:
The vault for the pre-engineered restroom for the Lake Alto Park did not meet Health Department standards. The new vault has been delivered/installed slightly further away than the originally planned location requiring additional ADA accessibility. The attached budget amendment will ensure the required ADA accessibility is completed.