On agenda: 5/9/2023 Final action:
Title: Special Pay Request for Nippers Quality Tree Service for $17,228
Attachments: 1. INVOICE 23100 Nippers Tree Service 98th St.pdf, 2. MEMO 230410 Special Pay Request Nippers Quality Tree Service (rdg) 4-20-23.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
title
Special Pay Request for Nippers Quality Tree Service for $17,228
body

Presenter:
Brian Kauffman, Asst. Public Works Director, 352-548-1306

Description:
Approve special pay request for Nippers Quality Tree Service for $17,228
body

Recommended Action:
recommended action
Approve special pay request for Nippers Quality Tree Service for $17,228
body

Prior Board Motions:
recommended action
August 24, 2021, Board of County Commissioners (BoCC) approved Purchase Orders for pumps, materials to prepare & enhance pumping locations, storage buildings, and portable radios.
body

Fiscal Consideration:
fiscal consideration
Approve special pay request, there are sufficient funds in account 146.79.7920.541.46.00
body

Strategic Guide:
strategic guide
Infrastructure
body

Background:
Areas around the Hills of Santa Fe subdivision have had a historical flooding issue and are considered a priority flooding area. To address this issue, the BoCC, in August 24, 2021, approved the purchase of five additional pumps to be dedicated to or support pumping at priority flooding areas and Countywide as needed. Also, permanent discharge piping has been installed at Hills of Santa Fe.

Additionally, in March of 2023, the Public Works staff started building a concrete flood-wall along the west side of NW 98th Steet to help prevent the flooding of homes in the Hills of Santa Fe Subdivision. The initial construction plans only required the removal of 4 trees. Two quotes were obtained. Nippers Quality Tree Service was awarded the job as low quote for $3,400. While the contractor was on site removing the trees, the scope of the wall's construction was significantly expanded to reassure the homeowners the wall would mitigate flooding. Unfortunately, due to the expansion of the wall, additional trees and stumps needed to be removed. To meet the deadline and fulfill the promise made to the homeowners to have this project completed before the start...