Title: Contract #10635, Change Order #2 between Alachua County and AJAX Building Corporation for Alachua County Fairgrounds CM-at-Risk GMP Construction Agreement.
Attachments: 1. CO #2 210526 ACAEC AJAX OCO 2 (rdg e-signed for CM).pdf, 2. CO #2 210526 LET 210314 ACAEC ACYFLS Sound System Letter.pdf, 3. CO #1 210512 ACAEC AJAX Change Order 01 (rdg e-signed).pdf, 4. Contract #10635 3rd Amendment.pdf, 5. Contract #10635 2nd Amendment.pdf, 6. Contract #10635 1st Amendment.pdf, 7. Contract #10635 CM At Risk Agreement.PDF
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

Contract #10635, Change Order #2 between Alachua County and AJAX Building Corporation for Alachua County Fairgrounds CM-at-Risk GMP Construction Agreement.

End

 

Presenter:

Ramon Gavarrete 352.374.5254

 

Description:

Contract #10635, Change Order #2 between Alachua County and AJAX Building Corporation for Alachua County Fairgrounds CM-at-Risk GMP Construction Agreement for Audio/PA System, domestic water and electrical supply to the Food Vendor area, and new metal siding on the East side of the Covered Arena

 

Recommended Action:

Recommended Action

Approve Change Order #2 for Contract #10635 between Alachua County and AJAX Building Corporation for Alachua County Fairgrounds CM-at-Risk GMP Construction Agreement which increases the Contract Amount by $343,433.10.

End

 

Prior Board Motions:

Oct. 27, 2020 - BoCC approved Third Amendment Agreement with AJAX Building Corporation to establish Guaranteed Maximum Price (Final GMP) for Vertical Infrastructure at the Agricultural & Equestrian Center and UF/IFAS Extension Office and Auditorium

 

Sept. 22, 2020 - Approve the resolution authorizing issuance of Capital Improvement Revenue Bonds Series 2020C; approve the budget amendment recognizing the unanticipated revenue and appropriating the related expense.

 

May 26, 2020 - Request Approval of Alachua County Agriculture & Equestrian Center Site Work - Guaranteed Maximum Price and Corresponding Contract Second Amendment: $4,749,723 with includes $235,175.00 from the City of Newberry as pass thru funding for Alternate 1 for Fresh and Waste Water Lines.

 

Feb. 11, 2020 - Commissioner Cornell moved option A and B and not building the 2nd bathroom (smaller facility) and work with the Youth Fair on the metal building.

 

On July 9, 2019 the BoCC approved the first amendment to the contract, amending the description of project and pre-construction phase services.

 

On August 8, 2019 the BoCC approved the Construction Management at Risk Contract for Construction of the Alachua County Fairgrounds.

 

Fiscal Consideration:

Fiscal Consideration

There are sufficient funds allocated to the project in accounts 325.45.4502.552.62.00 and 342.45.4502.552.62.00 to cover this change order. Project 9194101: Arena.

End

 

Background:

Change Order 2 includes the following renovations to the Arena & Stables.

 

All labor, materials, equipment, and management to install an Audio/PA System in the covered Arena, outdoor Riding Ring, and Five Horse Stable Barns. Renovations to the Arena and Stables are included in the project scope as well as the demolition and construction of a sound booth.

 

Part of the Scope of the Project included Renovations to the Arena & Stables.  There was an old PA system at the time Construction began.  The PA system was not replaced since it was thought that the system was in good operating condition.  The Scope also included the demolition and construction of a Sound Booth.

 

Renovation of an existing structure will always have unforeseen and installed systems might have to be replaced/renovated/or repaired during construction.  These systems could be electric installations, AC, Data, and, in this case, a PA system.

 

For the Youth Fair, it became apparent that the system was NOT in good operating condition and the Youth Fair rented a system for the fair.  Also, during construction of the Sound/Media Booth and the renovations of the Arena, some components of the PA system were found to be in conflict and, were affected. 

 

Provide labor, materials, equipment, and management to install domestic water to the Food Vendor area west of the Covered Arena. Provide and install an RV style electrical pedestal at the Food Vendor area.

 

Provide labor, materials, and equipment to install new metal siding on the East side of the Covered Arena to block glare coming off the metal roof of the Club House Building. The new metal siding on the East side of the Covered Arena was requested, and is needed, to block the sunlight glare coming off the metal roof as it disturbs the horses competing in the arena.

 

Change Order 1 reduced the GMP by $1,446,090.03 for Owner Direct Purchase Orders (DPO) for a sales tax savings to the County of $82,750.39.