File #: 21-0206    Version: 1
Type: Action Items -11:30 AM Status: Agenda Ready
File created: 3/2/2021 In control: Board of County Commissioners
On agenda: 3/23/2021 Final action:
Title: Sports Events Center 30% Plans Review and Project Update
Attachments: 1. Alachua Sport Bldg - 30% Renderings and Elevations.pdf
Related files: 21-0384, 21-0811, 21-0977
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

Sports Events Center 30% Plans Review and Project Update

End

 

Presenter:

James K. Harriott, Jr., P.E., Deputy County Manager

 

Description:

This presentation brings back the 30% Design of the Sports Events Center at Celebration Pointe.  In the design process 30% represents a critical breakpoint in establishing the program and final construction price.

 

Recommended Action:

Recommended Action

Hear presentation and direct staff to continue to engage with the development team on the design to maximize the sports events potential of the facility while maintaining the financial pro forma.

End

 

Prior Board Motions:

At the Board's Jan 26, 2021 meeting Commissioner Wheeler moved the following:

1) Authorize the Chair to sign a pre-development agreement consistent with the term sheet not to exceed $1 Million and

2) Authorize staff to work with the Operator to finalize the project development and operations agreements for future Board consideration.

3) The Board will review the plans at the 60% completion point.

2nd
Chestnut

The motion carried 5-0.

 

At the November 10, 2020 Board Meeting Commissioner Cornell moved to direct staff to negotiate a term sheet for the financing, construction and operation of a Sports Events Center with the most responsive proposer. And 2) bring back the results of negotiations for the Board’s consideration. (5:0)

 

At the October 15, 2019 Board Meeting ​Commissioner Byerly moved direct staff to further explore the creation of a Sports Events Center via a partnership with Celebration Pointe Community Development District with the following ordered steps:                     

1)          Determine public funding sources/amounts for the project.                     

2)          Develop architectural designs and construction cost estimates.

3)          Conduct a Celebration Pointe parking demand study and determine cost and Funding sources for additional parking stalls.                     

4)          Establish legal parameters for venue funding and ownership.

5)          Authorize a Chair letter to the City of Gainesville that provides the economic impacts of the Event Center to the community and request that the City get back to the Board of County Commissioners as soon as they have the necessary information to move forward with the eastern part of the City to move in a parallel path if possible.  (5-0.)

 

At the May 7, 2019 Special Meeting Commissioner Byerly moved the following:

1. That we direct staff to expand Victus Study to include an analysis of the Celebration Pointe Site and include as needed an analysis of the range of Public and/or Private Ownership models and to work with the Celebration Community Development District to come up with those numbers.

2. Direct staff to prepare a business model / operational analysis for all three of the sites we have been considering for public investment; Celebration Pointe,

Cabot Koppers and the MLK Site.

3. Direct Staff to draft an Interlocal Agreement for consideration by the

Commission for investments of Community Redevelopment Agency (CRA) funds and Wild Spaces Public Places funds for the Citizens Field and Cabot

Koppers sites. This should include a timeline for the development.

4. Authorize a Chair Letter to request that the Event Center be a topic of discussion at our Joint Meeting in June with the City of Gainesville.

 

The motion carried 5-0.

 

 

Fiscal Consideration:

Fiscal Consideration

After 30% design, significant deviation from the programmatic offerings or building components may negatively impact the financial pro forma. 

 

Per the Pre-Development Agreement, if the County elects to not proceed with the development, then Viking may be entitled to reimbursement of costs not to exceed $1 Million for the preparation of design and construction documents.

 

Contingent on the Board approving the 60% Design and Comprehensive Agreement with the Developer at a future board meeting, the County’s total obligation for the project would be $30 Million from TDT funds via a 30 year bond issuance.

 

The land and the building when constructed will be owned by the County.

 

End

 

Background:

The Negotiation Team’s recommendation was that the Board approve the Terms Sheet, authorize staff to prepare a Predevelopment Agreement, and authorize the Chair to execute the Predevelopment Agreement once it has been finalized by County staff. Now that the Predevelopment Agreement is close to being finalized and executed by the parties, the County’s Negotiation Team has been disbanded. The County Manager has designated Assistant County Manager Tommy Crosby to negotiate the terms and conditions of the Comprehensive Agreement with the Developer after Jim Harriott’s employment with the County ends on March 26, 2021.

 

County staff are working with the developer design team to meet County sustainability objectives and community economic benefits within the prescribed budget of the County.

 

A Pre-Development Agreement will be signed by the Chair based off the Board approved Terms Sheet.  The Terms Sheet set the negotiated conditions of the major deal points that informed the all other Project Agreements regarding the design, construction, management and operation of a Sports Events Center (Center) at Celebration Pointe.

 

If the Board decides to not pursue the project after the Pre-Development Agreement is executed but before the Board approves the Operating Agreement, the County will be required to reimbursement Viking up to $1 Million for its costs to develop the design, budget and GMP.

 

It is projected that 60% Plans will be ready for Board review by April 20. And 90% Plans and Specification, Budget, GMP and Operating Agreement may be ready for Board consideration by June-July 2021.  The 90% Design Plan will be the last major decision point for the Board and will include request to approve a 30 year bond issuance for $30M. 

 

Construction would commence in August 2021.

 

Current estimates place project being open for events in January 2023. The following is a general description of the project.

 

Project Description:

The Project will be designed to a Class A institutional quality and commensurate with National Collegiate Athletic Association qualifying sports facilities.  It will have no less than 110,000 square feet focusing on indoor track, volleyball, basketball, dance, and cheerleading. The Center shall contain an indoor track, 13 basketball courts, 26 volleyball courts, concession areas, restroom facilities, offices and other related facilities.

 

 

Prior History:

In June 2020, the Board received an unsolicited proposal from Celebration Pointe Holdings (CP Holdings) to develop a Sports Events Center to be located in Celebration Pointe.  A request for competing proposals was issued in September 2020 with a due date of 5PM October 21.   The request was posted to the Florida Administrative Register, advertised in the Gainesville Sun, on the County’s Website, and County Procurement’s Demandstar.  In addition, all Alachua County City Managers were contacted and a press release issued to generate greater awareness of the opportunity.

 

No competing proposals were received by the County.

 

The original proposal proposed the County finance the construction of the Sports Event Center using tourist development tax revenues.  CP Holdings would assume operational control of the Sports Event Center and assume responsibility to fund operations from revenues of the project.  Tourist development tax revenues are dedicated to supporting the tourism and associated hospitality industries.  The community will benefit overall if Celebration Pointe is selected as the Sports Events Center location.

 

Victus Advisors has estimated that this project at Celebration Pointe would:

1)                     Generate net impacts over a period of 30 years with a net present value (NPV) of approximately $1.2 billion in total economic output,

2)                     $392 million in wages, and

3)                     nearly $24 million in County sales tax revenues,

4)                     and County tourist development taxes.

5)                     In addition, it is estimated that up to 1,150 incremental annual jobs could be supported by this new economic activity.

6)                     Brings $12 million/year in hotel spending and 116,760 room nights.

7)                     Land does not need to be bought and is shovel ready.

 

This enhanced economic activity addresses the peaks and valleys of hotel stays and hospitality industry by stabilizing the revenue stream over the course of a year.  The programing from a sports events facility fills gaps in the tourism sporting calendar and grows a critical market opportunity along a high visitation corridor.

 

Location to a highly-used transportation corridor, with adjacent supporting retail and hotel facilities is critical to meeting these financial objectives.

 

There will be no property acquisition costs as the land is being offered as part of the agreement; provided the Board pays the existing special assessment liens against the property.

 

Prior to receiving the proposal, Victus Advisors reviewed four potential locations for a sports events center tracking sequentially westward from Waldo Road to Celebration Pointe.  The Celebration Pointe location was ranked number 1 at score of 92% and was highly recommended due to the significant supporting development, retail amenities, I-75 access and lodging opportunities. All other sites scored too low to be recommended (Waldo Road and 39th Ave: 50% score and Waldo Road and 8th Ave: 46% score) or scored marginally and are no longer available for consideration (Koppers: 67% score)

 

Prior Market Study & Site Analysis - In January 2019, Victus Advisors completed a Market Demand Study identifying demand for a new sports events center in Alachua County with:

 

• At least eight (8) indoor hardwood basketball/volleyball courts,

• An indoor banked track (hydraulic or removable),

• Retractable/portable seating with upwards of 3,000 seats for championship track events, and

• Parking for up to 1,150 vehicles.

 

In addition, in June 2019, Victus Advisors also completed a Site Options Analysis which identified Celebration Pointe as the recommended location for a new sports events center in Alachua County. Celebration Pointe is located on the northwest quadrant of the Interstate 75 and Archer Road (SR 24) interchange in Alachua County. The Celebration Pointe site was scored as “highly recommended” due to its easy access to hotels, retail, and dining, as well as convenient highway access, all of which could maximize tourism benefits, drive visitor satisfaction and return usage, and provide the greatest opportunity for the long-term success of the proposed sports events center.

 

Additional Victus Advisors Analysis for the County - In June 2019, Victus Advisors was engaged again by Alachua County to conduct a business planning, operations analysis, and economic impact analysis for a new sports events center at Celebration Pointe.

 

This study is intended to be a first step in analyzing the partnership opportunity at Celebration Pointe, confirming the operational validity of the site, and analyzing the net benefits of the project; and thus, facilitating additional conversations between the potential project partners (i.e. Alachua County, CPCDD, and Viking Companies).

 

In this additional study, Victus Advisors conducted the following services and analysis, specific to the proposed Celebration Pointe site and partnership opportunity:

 

                     Meetings in Alachua County with Viking Companies and CPCDD to discuss potential parameters and information needs for a partnership to develop a new sports events center,

                     SWOT Analysis for a new sports events center at Celebration Pointe,

                     Management Options Analysis for a public-private sports events center,

                     Usage Projections and Operating Pro Forma under the recommended management model, and

                     Economic and Fiscal Impact Analysis, incorporating Celebration Pointe development plans both with and without a new sports events center.