File #: 19-0349    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 9/9/2019 In control: Board of County Commissioners
On agenda: 10/8/2019 Final action:
Title: Deductive change order to the Eco Industrial Park Construction Agreement with VE Whitehurst & Sons Inc.
Attachments: 1. VE Whitehurst __10943 Agreement for Resource Recovery Park Phase.pdf, 2. Whitehurst CO4.pdf, 3. CES Eco Park Cont Reduction.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Deductive change order to the Eco Industrial Park Construction Agreement with VE Whitehurst & Sons Inc.
End

Presenter:
Ramon Gavarrete, P.E.

Description:
Deductive change order to the construction agreement for the Eco Industrial Park with V E Whitehurst & Sons, Inc. This unencumbers funds in the project budget to pay for other project needs. These needs include:

GRU Sewer and Water Inspection Fees $32,000
Increase in CEI Services $25,350
Surveying for boundary corners for Conservation Management Areas $2,400
Internal Costs for Project Management $17,250

Recommended Action:
Recommended Action
Approve deductive change order of $77,000 to construction agreement with V E Whitehurst and reallocate those budgeted dollars to the other identified project needs.
End

Prior Board Motions:
In 2014, the BoCC approved a motion to move forward with the final development plan and with adding the project to the CIP.

Comprehensive Plan Element: 8.0 Energy Element -
Policy 8.1.1 -
To help achieve the 75% waste recycling goal mandated by the state by 2020 and reduce greenhouse gas emissions associated with the transport of municipal solid waste, promote a cluster of waste to wealth industries at the Resource Recovery Park to make useful products from recycled materials. As a component of this, work to direct municipal solid waste to the Leveda Brown Environmental Park.

April 24, 2018 - Board approved the Finance Report for the project and authorized staff to negotiate an agreement with VE Whitehurst & Sons, Inc.

June 26, 2018 - Board approved the Construction Agreement with VE Whitehurst & Sons, Inc.

Fiscal Consideration:
Fiscal Consideration
Deductive change order - $77,000, reduces VE Whitehurst contract encumbrance by $77,000. This increases the unencumbered balance in the project to pay expenses for:
GRU Sewer and Water Inspection Fees $32,000
Increase in CEI Services $25,350
Surveying for boundary corners for Conservation Man...