Legislation Details

File #: 22-0467    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 5/25/2022 In control: Board of County Commissioners
On agenda: 6/14/2022 Final action:
Title: Award and Contract #13322 BID 22-314 Health Department Chiller and Boiler Replacement to Mechanical Services of Central Florida, Inc. in the amount of $336,185.00
Attachments: 1. #13322 Health_Department Chiller Replacement.pdf, 2. EXECUTIVE SUMMARY 22-314-TW CSS-Health Department Chiller and Boiler Replacement.pdf, 3. ITA 22-314-TW CSS-Health Department Chiller and Boiler Replacement.pdf, 4. 22-314 Question & Answer Report.pdf, 5. 22-314-TW CSS-Health Department Chiller and Boiler Replacement - Site Visit Recap.pdf, 6. BT Report 22-314-TW CSS-Health Department Chiller and Boiler Replacement.pdf, 7. BT Selected Vendors 22-314-TW CSS-Health Department Chiller and Boiler Replacement.pdf, 8. DR 22-314-TW CSS-Health Department Chiller and Boiler Replacement.pdf, 9. ITB 22-314-TW.pdf, 10. SIS 22-314-TW CSS-Health Department Chiller and Boiler Replacement.pdf, 11. Supplier -MSI Certified Air 22-214.pdf, 12. Supplier - Carrier Corporation 22-214-TW.pdf, 13. Supplier -Ladson Construction 22-214.pdf, 14. Supplier - Air Mechanical Services Corp 22-214.pdf
Related files: 23-0501
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

Award and Contract #13322 BID 22-314 Health Department Chiller and Boiler Replacement to Mechanical Services of Central Florida, Inc. in the amount of $336,185.00

End

 

Presenter:

Greg Creel 352.374.5229, Larry Sapp 352.374.5202,

 

Description:

Solicitation award and Contract #13322 for BID 22-314 Health Department Chiller and Boiler Replacement

 

Recommended Action:

Recommended Action

Approve the award and contract for the Health Department Chiller and Boiler replacement to Mechanical Services of Central Florida, Inc. in the amount of $336,185.00 as the lowest responsible and responsive bidder meeting specifications, and authorize the Chair to execute same on behalf of the County

End

 

Prior Board Motions:

The project was approved by the Board as part of the FY21 budget but was not completed in FY21.  Project was part of the FY22 Carry forward budget amendment to complete in FY22 

 

Fiscal Consideration:

Fiscal Consideration

Funding for this project is in 001.19.1919.519.46.00 - Project 8211907-FY21-HVAC Chiller/Boiler in the amount of $510,000. Budget from FY21 carried forward into FY22.

End

 

Strategic Guide:

Strategic Guide

N/A

End

 

Background:

The current chillers and boilers have reached the end of their life cycle. They are continuously failing and parts are hard to obtain for these older machines. The boilers are atmospheric and have an efficiency rating on the lower end of the spectrum as compared to more modern equipment. Replacing the chillers and boilers will see cost savings in maintenance as well as energy consumption.

 

The project will be a turnkey installation of chillers, boilers, controls, and a new refrigerant monitoring system that is up to date with the new monitoring and exhaust law changes