Title: Award/Contract - BID 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1
Attachments: 1. Contract # 11346 with Hartman for SW 24th Ave Sidewalk ATF by CAO.pdf, 2. AR 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1.pdf, 3. DR MEMO 19-925 SW 24th Ave Sidewalk Project 919-7902-FY19-1.pdf, 4. BR 19-925 BID Responsiveness and SBE Recap Form.pdf, 5. SUBMITTAL PRICING 19-925 Hartman Civil Construction Co. Inc.pdf, 6. BT 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1.pdf, 7. ADM 1 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1.pdf, 8. BID PLANS 19-925 SW 24th Avenue Sidewalk.pdf, 9. BID 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1.pdf, 10. SW 24th Ave Budget Amendment.pdf, 11. Community Engagement Survey.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

Award/Contract - BID 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1

End

 

Presenter:

Ramon D, Gavarrete, P.E., County Engineer 352.548.1214/Larry Sapp, 352.374.5202

 

Description:

Award, contract and budget amendment for BID 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1.

 

Recommended Action:

Recommended Action

Approve the award, contract and budget amendment for BID 19-925 SW 24th Avenue Sidewalk Project 919-7902-FY19-1 to Hartman Civil Construction Co. Inc., in the amount of $293,750.00, plus a contingency amount of $29,375.00, for a total fiscal impact of $323,125.00,  as the lowest, most responsible and responsive bidder meeting specifications. Budget amendment is to approve the movement of $101,000 from Kincaid Loop to SW 24th Avenue Sidewalk Project to cover budget shortfall.

End

 

Prior Board Motions:

September 2018- Board added project to the CIP with the FY 19 budget process. 

 

Fiscal Consideration:

Fiscal Consideration

The total amount needed for the contract with contingency for project 919-7902-FY19-1 is $323,125 with only $267,195 of available project budget in account 350.79.7910.541.63.01.  The budget shortfall will be made up by approving budget amendment moving $101,000 from the Kincaid Loop project to this project along with FY19 carryforwards.  Funds are associated with the 5-Cent Local Option Gas Tax.

End

 

Background:

The project is to install a 6 FT wide concrete sidewalk on the south side of SW 24th Avenue between SW 87th Way and SW 77th Street.  This will also require reworking the drainage system and rebuilding driveways.  Work is expected to commence in December, 2019 and reach completion in Spring 2020.  Work will be conducted during the daytime.

 

Bid SW 24th Avenue Sidewalk Project 919-7902-FY19-1 was advertised on July 17, 2019 and July 24, 2019.  The deadline for receipt of Bid SW 24th Avenue Sidewalk Project 919-7902-FY19-1 was August 21, 2019; one (1) vendor responded.