Title: Budget Amendment for Design of the Trout Street Stormwater Improvement Project
Attachments: 1. FY23-27 Water Quality Project List ADA.pdf, 2. FY 23-27 Water Quality Project Descriptions ADA.pdf, 3. Budget Amendment
Related files: 22-0655
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

title

Budget Amendment for Design of the Trout Street Stormwater Improvement Project

body

 

Presenter:

Shane Williams - Environmental Protection Department (EPD)

 

Description:

This item is a budget amendment to allocate existing Stormwater Assessment Funds for the Trout Street Stormwater Improvement Project (Project #8235504)

body

 

Recommended Action:

recommended action

Approve the attached Budget Amendment

body

 

Prior Board Motions:

recommended action

September 13, 2022 - This project was listed on the Water Quality Project List and Water Quality Project Descriptions provided to the Board with the Final Resolution for the Stormwater Assessment. The project is scheduled to begin design in 2023 per the list.

body

 

Fiscal Consideration:

fiscal consideration

Funds for the design of this project are available in the Stormwater Fund; the attached budget amendment assigns them to this project. Funds for construction are to be determined (TBD) and will be added at a later date.

 

Total cost: $145,000

Stormwater Management Fund: 146.55.5511.537.63.98; project #8235504

body

 

Strategic Guide:

strategic guide

Environment

body

 

Background:

The Lake Santa Fe Nutrient Source Study assessed a stormwater outlet to Lake Santa Fe at the Trout Street boat ramp on Melrose Bay. This outfall discharges runoff from the surrounding neighborhood. The residents of the area have expressed concern about the water quality impacts of the untreated runoff. The intent of this project is to design Green Stormwater Infrastructure/Low Impact Design best management practices at strategic locations in the area draining to the Lake to provide water quality treatment and reduce nuisance drainage issues. This will result in a water quality benefit for the lake. A task assignment for the design will be issued through EPD’s environmental services contracts.