File #: 19-0066    Version: 2
Type: Consent Item Status: Agenda Ready
File created: 7/23/2019 In control: Board of County Commissioners
On agenda: 8/27/2019 Final action:
Title: BID 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01)-Award/Contract
Attachments: 1. Contract 11283 Capital Construction Agreement with Curts Construction Inc. - ATF.pdf, 2. FR 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01).pdf, 3. MAP NW 182 AVE.pdf, 4. MEMO 190612 Poe Springs Trail Bid Award.pdf, 5. Curts Corporate Resolution.pdf, 6. LTR 190702 Poe Springs Trail Bid Concurrence of Award.pdf, 7. DEPT REC 19-900 Poe Springs Road Trail (LAP - FPN 433990-2-58-01).pdf, 8. BR 19-900 BID Responsiveness and SBE Recap Form.pdf, 9. BT 19-900- Poe Springs Road Trail (LAP - FPN 433990-2-58-01).pdf, 10. Pricing Submittal 19-900 -Curt's Construction, Inc.pdf, 11. 1 ADM 19-900 Poe Springs Road Trail (LAP - FPN 433990-2-58-01).pdf, 12. BID 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01).pdf, 13. BID 19-900 SpecPackage-433990-2-Poe Springs-Attachement A.pdf, 14. BID 19-900 4339902-PLANS-01-ROADWAY.PDF, 15. BID 19-900 4339902_PLANS_02_SIGNINGMARKING.PDF, 16. BID 19-900 UWS-Windstream.pdf, 17. BID 19-900 UWS-CityofHighSprings.pdf, 18. BID 19-900 UWS-ClayElectric.pdf, 19. BID 19-900 Signed Authoriztion to Advertise.pdf
Related files: 19-0642
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

BID 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01)-Award/Contract

End

 

Presenter:

Ramon D, Gavarrete, P.E., County Engineer 352.548.1214/Larry Sapp, 352.374.5202

 

Description:

Approve the award and contract for BID 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01), to Curt’s Construction, Inc.

 

Recommended Action:

Recommended Action

Approve the award and contract for Bid 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01), to Curt’s Construction, Inc., in the amount of $1,148,987.57, as the lowest responsible and responsive bidder meeting specifications.

End

 

Prior Board Motions:

March 26, 2013 - Board ranked Poe Springs Road Trail as the number 1 priority for the Federal Transportation Alternative Program

 

September 13, 2016 - Board approved LAP Agreement with FDOT for the design of Poe Springs Road Trail

 

October 9, 2018 - Board approved LAP Agreement with FDOT for the construction of Poe Springs Road Trail.

 

Fiscal Consideration:

Fiscal Consideration

The Agreement amount is $1,148,987.57; FDOT has provided $1,504,858.00 for the construction phase which is allocated in Fund 313.

 

The available Budgeted $1,513,778.40, in account 313.79.7914.541.63.04; is sufficient for contract. 

 

The project is funded through the Federal Transportation Alternatives Program via FDOT fund, project #6304,and consist of a 10 ft wide trail on the north side of NW 182nd Ave from US 27/41 to Poe Springs Park totaling 3.3 miles in length. Construction is scheduled to begin in October and reach final completion Spring 2020.

End

 

Background:

Bid 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01) advertised on May 1, 2019 and May 8, 2019.  The deadline for receipt of Bid 19-900 Poe Springs Road Trail (LAP-FPN 433990-2-58-01) was June 5, 2019; three (3) vendors responded.