File #: 20-0558    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 7/3/2020 In control: Board of County Commissioners
On agenda: 9/22/2020 Final action:
Title: Award Contract BID 20-957 Poe Springs Boardwalk Improvements, to Dockworks of North East Florida, LLC, d/b/a C&H Marine Construction, in the amount of $564,817.00
Attachments: 1. Agreement 11613 with C H Marine Construction Inc. for Poe Springs Boardwalk Improvements - ATF by CAO.pdf, 2. AR 20-957 Poe Springs Boardwalk Improvements.pdf, 3. DR 20-957 Poe Springs Boardwalk Improvements.pdf, 4. BR 20-957 Bid Response Form.pdf, 5. BT 20-957 Poe Springs Boardwalk Improvements.pdf, 6. Supplier Shore Builders 20-957R.pdf, 7. Supplier C&H Marine Construction 20-957R.pdf, 8. Supplier C&L Landscape 20-957R.pdf, 9. Supplier Custom Built MarineR.pdf, 10. Supplier Hayward Construction Group 20-957R.pdf, 11. Supplier Hydra Engineering 20-957R.pdf, 12. Supplier Midcoast Construction Enterprises 20-957R.pdf, 13. SIS 20-957 Poe Springs Boardwalk Improvements.pdf, 14. Supplier SE Cline Const 20-957R.pdf, 15. ADM 5 20-957 Poe Springs Boardwalk Improvements.pdf, 16. ADM 4 20-957 Poe Springs Boardwalk Improvements.pdf, 17. ADM 3 20-957 Poe Springs Boardwalk Improvements.pdf, 18. ADM 2 20-957 Poe Springs Boardwalk Improvements.pdf, 19. ADM 1 20-957 Poe Springs Boardwalk Improvements.pdf, 20. BID 20-957 Poe Springs Boardwalk Improvements FINAL.pdf, 21. Budget Amendment.pdf
Related files: 20-0633
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Award Contract BID 20-957 Poe Springs Boardwalk Improvements, to Dockworks of North East Florida, LLC, d/b/a C&H Marine Construction, in the amount of $564,817.00
End

Presenter:
Charlie Houder 352.264-6804/Larry Sapp 352.374.5202

Description:
Award contract BID 20-957 Poe Springs Boardwalk Improvements

Recommended Action:
Recommended Action
Award contract BID 20-957 Poe Springs Boardwalk Improvements, to C&H Marine Construction, in the amount of $564,817.00, as the lowest, most responsible and responsive bidder meeting specifications. Establish a County Contingency, within the Contract in an amount not to exceed $28,240.85 for unanticipated costs that may arise during the Project. Additionally,, approve a Budget Amendment in the amount of $310,000.00 moving funds into Project #6194106, Poe Boardwalk and Canoe Launch
End

Prior Board Motions:
October 10, 2017, Board adopted resolution 17-120 recognizing unanticipated revenue from FEMA disaster recovery fund for hurricane Irma.

January 22, 2019, Board adopted resolution 19-05 recognizing unanticipated revenue from FEMA disaster recovery fund for hurricane Irma.

February 28, 2017, Board adopted resolution and budget amendment creating a new fund to budget and appropriate the unanticipated revenue related to the November, 2016 voter approved Wild Spaces Public Places (WSPP) 1/2 cent sales tax referendum.

May 28th 2019 the Board approved the resolution and Budget Amendment authorizing/recognizing the unanticipated revenue and approve the amendment to the Capital Improvement Plan (CIP).

Fiscal Consideration:
Fiscal Consideration
Please note the contract includes a not to exceed contingency amount of $28,240.85, and the budget amount for contingency is $25,848.00. There are sufficient funds in the FEMA Capital budget and Wild Spaces Public Places to cover the project. Additional contingency would need to come from WSPP, taking from another project, to be determined at that...

Click here for full text