Agenda Item Name:
Title
NW 23rd Avenue Project Estimate Update
End
Presenter:
Ramon D. Gavarrete, P.E., Public Works Director
Description:
Provide updated cost estimate for the NW 23rd Avenue reconstruction project (the "Project") and the NW 23rd Avenue alternative scope of work project (the "Alternate").
Recommended Action:
Recommended Action
Direct staff to proceed with the Public Works proposed alternate typical section, which consists of:
1. Milling and resurfacing the existing roadway
2. Widening for turn lanes and bus stops
3. Constructing an 8 FT multiuse path on the north side of NW 23rd Avenue
End
Prior Board Motions:
April 7, 2015 - The Board approved the submittal of NW 23rd Avenue to FDOT County Incentive Grant Program (CIGP) to four-lane the roadway and directed staff to create models connecting NW 31st Avenue to NW 33rd Avenue and NW 33rd Avenue to NW 51st Street.
December 13, 2016 - The Board submitted NW 23rd Avenue, Four Lane (Option 3) for a CIGP Application and directed staff to analyze a 3-lane cross section.
February 14, 2017 - The Board directed staff to proceed with CIGP application by submitting the development of NW 23rd Avenue - Option 2 - Two Lane with wide median and turn lanes.
March 26, 2019 - The Board adopted Resolution 19-35 approving the typical section and alignment for the Project.
May 28, 2019 - The Board approved budget amendment allocating additional funds for the design phase of the Project.
August 27, 2019 - The Board adopted Resolution 19-85 authorizing the County to enter into a funding agreement for the Project.
November 12, 2019 - The Board adopted Resolution 19-125 approving and authorizing the Chair to sign the CIGP Agreement for the Project
Fiscal Consideration:
Fiscal Consideration
The County has entered into an agreement with the FDOT for the Department to provide $1.2 million in matching state funds for the design and ROW acquisition for the current board approved project. The County has invoice...
Click here for full text