Agenda Item Name:
Title
FDOT Agreements: NW 23rd Ave, CR 235 at Newberry Lane, SR 24 Bike Path and SE 35th Street at SR 20
End
Presenter:
Ramon D. Gavarrete, P.E., Public Works Director & Brian M. Singleton, PE, Assistant Public Works Director
Description:
Request approval of five FDOT agreements for NW 23rd Ave from NW 55th St to I-75, CR 235 at Newberry Lane, Archer Road Bike Path from SW 75th Ter to SW 41st Blvd and SE 35th St at Hawthorne Rd.
Recommended Action:
Recommended Action
1. That the Board waive the County's Policy against contractual indemnity set forth in Resolution 2014-33, and adopt the attached Resolution approving and authorizing the Chair to sign:
a) County Incentive Grant Program Agreement for NW 23rd Ave.
b) Local Agency Program Agreement for CR 235 at Newberry Lane
c) Florida Shared-use Non-motorized Trail Network Funding and Maintenance Agreements for Archer Road
d) Construction & Maintenance Agreement SE 35th St at Hawthorne Road
and the Board finds that accepting the liability contained in the agreements is in the best interests of Alachua County and the Board agrees to accept the liability under the Agreements.
2. That the Board approve: (a) an interfund loan of $500,000 to the FDOT Grant Fund (Fund 329) for expenses until reimbursement by FDOT, and (b) the attached budget amendment for unanticipated revenues. Loan to be repaid upon completion of projects.
End
Prior Board Motions:
NW 23rd Ave
February 14, 2017 - Direct staff to proceed with grant application by submitting the development of NW 23rd Avenue - Option 2 - Two Lane with wide median and turn lanes.
March 26, 2019 - Board adopted Resolution 19-35 approving the typical section and alignment for the NW 23rd Ave project.
May 28, 2019 - Board approved budget amendment allocating additional funds for the design phase of the project.
Fiscal Consideration:
Fiscal Consideration
Project: 9177914 - Fund 336 & 329
NW 23rd Ave (project 9177914) has $1.2M in local f...