File #: 20-0344    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 4/18/2020 In control: Board of County Commissioners
On agenda: 5/26/2020 Final action:
Title: Increase in project cost and due diligence for the State Road 121 Rural Collection Center (North Central Collection Center)
Attachments: 1. JBrown North Central Collection Center.pdf, 2. RCC BA.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Increase in project cost and due diligence for the State Road 121 Rural Collection Center (North Central Collection Center)
End

Presenter:
Gus Olmos, P.E.

Description:
The North Central Collection Center (project #9197601) is in need of improvements and repairs to keep the center operating efficiently. Initial work order was issued to JBrown Professional Group to develop an initial master plan depicting the proposed improvements in the amount of $39,244. In order for JBrown to complete their initial master plan: geotechnical services, landscape plans, and development review fees of approximately $20,000 need to be added to the project which brings total project amount to over $50,000 which requires Board approval.

Recommended Action:
Recommended Action
Approve the North Central Collection Center Project (proj# 9197601) and approve the budget amendment moving $20,000 from appropriate reserves in Rural Collection Centers Fund to professional services engineering.
End

Prior Board Motions:
N/A

Fiscal Consideration:
Fiscal Consideration
There is sufficient funds in reserves to cover movement of $20,000 from reserves to professional services engineering. Account: 403.76.7610.534.31.08
End

Background:
Historically, the North Central Collection Center has had some Stormwater drainage issues which have kept the center from being able to fully utilize the site where it is located. Additionally, there are other repairs/improvements which staff wanted to look at while addressing the drainage issues. These issues are detailed below:

North Central Collection Center (proj# 9197601)

Civil Engineering Services (Initial Planning): The Initial Planning civil
engineering work scope shall include:

Initial coordination with the Collection Center Supervisor (Supervisor) and
County staff to define all improvements required for the property. Generally, it
is understood that the improvements to be designed include:
* A new concret...