File #: 20-0493    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 6/9/2020 In control: Board of County Commissioners
On agenda: 6/23/2020 Final action:
Title: Camp McConnell Restoration - Amend the CIP, move budget and establish projects
Attachments: 1. 5 Year CIP for Camp McConnell.pdf, 2. Camp McConnell Project Journal 2020-2718.pdf
Related files: 20-0404, 21-0223, 21-0073, 21-0489, 21-0201, 21-0373
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Name:
Title
Camp McConnell Restoration - Amend the CIP, move budget and establish projects
End

Presenter:
Gina Peebles

Description:
The Board approved the project overall, but there is no funding specifically for this project in FY20, as this was an FY21 budget request. In order for Parks and Open Space to be able to spend a portion of this award in FY20, the Board must amend the CIP to include Camp McConnell and approve the budget amendment to move the budget to the accounts needed to commence the work.

We are also establishing 1 project with multiple subprojects. The entire project is under "Camp McConnell Renovations" and Parks will monitor and track the different components through the subprojects.

Recommended Action:
Recommended Action
1. Approve the amended Capital Improvement Plan (CIP) to include Camp McConnell;
2. Approve the budget amendment to move the budget to the required account lines and establish projects in order to track types of expenditures related to the restoration.
End

Prior Board Motions:
At the June 9, 2020 BoCC meeting, the Board approved $2.7 million in repairs and improvements at Camp McConnell. This restoration is to be funded from Parks' allocation of Wild Spaces Public Places funding.

Fiscal Consideration:
Fiscal Consideration
The Board approved a total of $2.7 million, from Parks' allocation of Wild Spaces Public Places revenues. In FY20, Parks anticipates it will spend $520,864, which was not budgeted. The attached amendment moves the entire budget into place.

Fund 021.41.4100.572.xx.xx - multiple accounts.
End

Background:
At the June 9, 2020 BoCC meeting, the Board approved $2.7 million in repairs and improvements at Camp McConnell. This restoration is to be funded from Parks' allocation of Wild Spaces Public Places funding.

As this was an FY21 budget proposal, the FY20 budget is not prepared for Parks to begin this project. In order to get Parks and the budget ready, this agend...

Click here for full text