File #: 20-0404    Version: 1
Type: Action Items -11:30 AM Status: Agenda Ready
File created: 5/11/2020 In control: Board of County Commissioners
On agenda: 5/26/2020 Final action:
Title: Request Approval to Proceed with Camp McConnell Improvements
Attachments: 1. Camp McConnell.pdf, 2. Camp McConnell Map.pdf, 3. Reno Demo Estimates.pdf, 4. Reno Demo Building Summary.pdf, 5. Camp McConnell Zoning Report.pdf, 6. Camp Crystal Financials.pdf, 7. Camp McConnell Brochure.pdf, 8. GLE Asbestos Survey Scope of Services.PDF, 9. ROSCO Camp McConnell Letter.pdf, 10. EPAC Recommendations 102318.pdf, 11. J Ellis Email 110819.pdf, 12. T McKercher Letter.pdf, 13. Prospects List.pdf, 14. Basecamp Ventures Proposal.pdf, 15. Camp Florida Full Proposal v2.pdf, 16. Camp_Florida.pdf, 17. Fl Wildlife Care Ltr.pdf, 18. Camp McConnell Emails.pdf
Related files: 19-0104, 19-0148, 19-0761, 20-0493, 21-0073, 21-0223, 21-0489, 21-0201, 22-0369, 21-0373
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Name:

Title

Request Approval to Proceed with Camp McConnell Improvements

End

 

Presenter:

Gina Peebles, 352-538-8265

 

Description:

Camp McConnell Discussion

 

Recommended Action:

Recommended Action

Approve scope of work for capital improvements, not to exceed $2.7 million funded through unencumbered Wild Spaces Public Places funding.  These improvements will stimulate our construction industry during a time when we cannot host camps, so the facility can be open for the summer of 2021.

End

 

Prior Board Motions:

Jan. 14, 2020 -

1.                     County retains ownership of Camp McConnell.

2.                     Have staff reconcile the spent, funded, and unfunded active recreation projects and return back to the Board by email within 30 days to determine the exact available funds.

3.                     Convene a community design charrette with staff within 90 days to develop a potential community plan and capital improvement plan. The initial potential camp operating budget would be potentially 2 to 3 million. Florida Wildlife Care should be involved in the charrette. (3:1)

 

Oct. 8, 2019 - That staff schedule this for a future Regularly Scheduled Evening Board meeting for the Board to discuss. At that time staff is to bring any information/knowledge from interested parties and invite the public to attend.

 

To reject all proposals and inform anyone who submitted a proposal. Direct staff to reach out to the City of Gainesville to expressly understand their intent per their motion. Is it programming, capital, etc.? (5:0)

 

Additional motions are included in the attached report.

 

Fiscal Consideration:

Fiscal Consideration

There is $2.7 Million available in the Parks portion of WSPP allocation for this project. This will use the portion of funds previously set aside for the Rail Trail purchase. It will be added to the CIP during the FY21 Budget Development.

End

 

Background:

Per Board direction in January, a public charrette was held to gather input from citizens on the future of Camp McConnell.  Overwhelmingly, the citizens requested capital improvements be made to the property to allow for day use including renovations to the Mess Hall, pool and trails and overnight camp amenities.  Approximately $2.7 million is available in unencumbered Wild Spaces Public Places funding, which could be used for these improvements, pending Board approval and direction.

 

The 300+ page environmental report on the property is available by clicking:  <https://alachuacounty.sharefile.com/d-sb2b6ca1e18247279>